Sanitation of Northeastern Areas of Athens

Storm Water, Wastewater Disposal & Treatment Plant, Athens, Greece

Project Details

Construction Cost:

Year of Completion:

Location:

 

€ 235m

2005

Attica, Greece

Services Rendered

• Master plan and Feasibility Study

• Design

• Geological, topographical and sea bed surveys

• Environmental impact studies

• Cost benefit study

• Preparation of funding application to be addressed to the EU Cohesion Fund

• Preliminary Design of the storm water pipelines

• Detailed Design of the sewerage system

The project of the storm water and wastewater systems concerns the urban touristic and agricultural zones under rapid development and urbanization of the Northeastern areas (61.5km2 approx.) of Attica prefecture.

 

It will be serving several urban settlements (communities or municipalities) of the north area of the east prefecture of Attica: Kropia,

 

Paiania, Spata, Anthousa, Penteli, Geraka, Glyka Nera, Pallini, Pikermi, Rafina, Artemida, Nea Makri and Marathona, with 2,000 to 15,000 inhabitants each, having a total population of 265,000 residents. Population served during the summer peak bathing season will increase to 470,000 PE (year 2040).

 

The Project includes one wastewater

 

treatment plant for 470,000 PE (Phase B’ - 2040) with full biological treatment and tertiary treatment for effluent reuse in irrigation and industries, near the town of Rafina, one 2m3/sec twin pipeline Ø1000mm of total length 6.4km (sea outfall 1.75km), one submarine outfall (1km) and 160km of main sewage drains (DN 350 to 1,200), including a tunnel of 1.1km length (d=4m).

Related Projects

Village Sewerage Networks, Wastewater Collection and Conduit to existing WWTP

Serving the Greater Area of Athens, Greece

Control Automation and System Integration, Dubai, U.A.E.